Crews working on the $1.2-billion Harbor Bridge replacement project in Corpus Christi, Texas reached a milestone when they completed the main span closure in February. The new Harbor Bridge is now ...
A Rising Tide Check out the monthly progress at HBP
New Harbor Bridge in Corpus Christi, set to be the largest cable-stay, concrete-segmental bridge in US nears completion after years of delays and challenges.
According to the project team working on the design and construction of the new Harbor Bridge in Corpus Christi, Texas, everything is on schedule for its 2025 opening. According to Flatiron/Dragados, the team behind the project, work continues on the new bridge, which is designed to withstand hurricane force winds.
UPDATE: March 15, 2023: Four out of five safety concerns that Texas DOT raised with contractor Flatiron/Dragados and engineer Arup on the new Harbor Bridge project in Corpus Christi, Texas, have ...
As the Harbor Bridge Project continues to progress, further updates will be provided. Congratulations to the PCY team on reaching this pivotal stage in the development of the new cable-stayed bridge, a key infrastructure component expected to enhance transportation in the region.
DPS Troopers expand Corpus Christi highway patrols to Hwy. 361 Harbor Bridge Project: New exit to Uptown Corpus Christi now open
CORPUS CHRISTI, Texas — Officials with the Harbor Bridge Project told 3NEWS that crews ended 2023 with some significant changes to traffic flow around the new Harbor Bridge's south interchange ...
The new Harbor Bridge is estimated to open in spring 2025 with a price tag of about $1.2 billion, transportation officials said Friday – exceeding its previous $803 million estimate and missing ...
The Texas Department of Transportation and developer Flatiron/Dragados, LLC. marked a significant milestone in the Harbor Bridge Project this week, holding a “topping-out” ceremony at the center of the new bridge. The event, a traditional construction practice, included the placement of trees to signify the completion of the structural phase of the project. The new…
CORPUS CHRISTI, Texas — An update on the new Harbor Bridge project was presented to a group of Westside business owners on Wednesday. During the presentation, a representative of Flatiron ...
After the Texas Department of Transportation contracted with Flatiron/Dragados LLC to build the new U.S. 181 Harbor Bridge Project, the website HarborBridgeProject.com was developed for information and updates related to the design and build phase of the project.
CORPUS CHRISTI, TX—Lane closures this weekend will usher in a new, permanent traffic alignment associated with the Harbor Bridge Project, which will improve traffic flow for motorists traveling on I-37, US 181, and SH 286.
Work on the main span of the new Harbor Bridge in Corpus Christi, Texas, resumed Dec. 15 after a nearly four-month suspension over design safety concerns. Texas Dept. of Transportation officials ...
CORPUS CHRISTI, TX – Effective today, TxDOT and Flatiron Dragados LLC (FDLLC) have executed a signed letter agreement that establishes the legal framework for resolving the safety issues identified in the design of the New Harbor Bridge Project. The...